LUKAVAC CEMENT: REGULAR OVERHAUL ACTIVITIES TO BE SUCCESSFULLY COMPLETED SOON

Lukavac Cement

There are a few days left until the end of the regular annual overhaul maintenance of our facilities. Enis Rizvić, maintenance manager, reports that all activities are implemented very successfully and according to plan.

Thus, among other things, several important undertakings were carried out: the replacement of the refractory wall in the rotary kiln with a length of 45 m and part of the mantle of the rotary kiln with a length of 8.5 m as well as the reducer on the main drive of the kiln.